STATE OF
ENVIRONMENTAL
COURT
}
Appeal of
Walters, et al.
}
Docket No. 206-11-03 Vtec
}
}
Decision and Order on Cross-Motions
for Summary Judgment
In the above captioned matter,
Appellants appealed from a decision of the Development Review Board (DRB) of the
Town of Randolph (Town) granting Appellee-Applicant Vermont Pure Springs, Inc.’s
application for an amendment to their 1993 conditional use permit and site plan
approval. Appellants are
represented by Stephanie J. Kaplan, Esq.; Appellee-Applicant[1]
is represented by Michael J. Marks, Esq.; and the Town is represented by Peter
M. Nowlan, Esq. W. Hugo Liepmann
appeared as an interested person and represents himself.
This appeal is “on the record” as the
Town has adopted and implemented the procedures necessary for such appeals,
pursuant to 24 V.S.A. § 4471 and § 4472.
The parties have submitted the merits of this appeal for the Court’s
consideration by cross-motions for summary judgment.[2] Of the issues presented in Appellants’
Statement of Questions, the parties have narrowed the contested issues to the
following:
(a) Whether Appellee-Applicant‘s
operation can properly be considered a conditional use;
(b) If the application is not for a
conditional use permit, whether Appellee-Applicant’s use qualifies for review
under Zoning Regulations (Regulations) § 2.4.3;
(c) If the application does qualify
for review under § 2.4.3, whether that section is
unconstitutional;
(d) In the alternative, if the
application is not for a conditional use permit, whether Appellee-Applicant’s
application should be considered under Regulations § 2.5.4 for an expansion of a
non-conforming use, and whether that section is
unconstitutional;
(e) Whether the DRB erred in granting
approval for trucks with a higher maximum gallonage than was requested in
Appellee-Applicant’s application or discussed at the hearings;
and
(f) Whether the DRB erred in granting
approval for different hours of operation—including a higher number of truck
trips during the daytime—than was requested in the written application or
discussed at the DRB hearings.
Factual
Background
The record[3]
for this appeal reveals the following undisputed material
facts:
1.
Appellee-Applicant operates spring water collection and bottling
facilities in the Town of
2.
Appellee-Applicant’s springs supply water to its collection site, located
approximately 0.7 miles down
3.
Appellee-Applicant currently conducts its business operations in the
following manner:
a.
Appellee-Applicant collects water that percolates up from the springs in
holding tanks. Under the
pre-existing permit, tanker trucks with an 8,000-gallon capacity are filled with
the spring water at the
b.
The filled trucks then drive approximately 3.5 miles to
Appellee-Applicant’s bottling facility off Vermont Route 66, near Interstate
89. The bottling facility acts as a
containment, distribution, and storage warehouse where the bottled water is
shipped for commercial, wholesale or retail sale throughout
c.
After being emptied at the bottling facility, the trucks return to the
spring site via Route 66 and
4.
In addition to the two springs already in use, Appellee-Applicant
proposes to develop four new springs at their 65.7-acre property on
5.
Appellee-Applicant first applied in 2002 for an amendment to its
pre-existing conditional use permit to increase the volume of spring water it
collected from the
pre-existing conditional use permit was approved by
the DRB on
6.
Appellee-Applicant’s 2003 revisions to its previous application addressed
concerns about truck traffic between its
7.
The capacity of the proposed trucks is slightly greater than half the
capacity of trucks currently in use. Appellee-Applicant also proposed
increasing the number of truck trips between the springs on Rogers Road and the
bottling plant from 160 to 240 round-trip truck trips per week (or from 320 to
480 one-way weekly truck trips).
See Appellants’ Ex. 5, at 2.
Appellee-Applicant’s revised application would result in a net reduction
from its 2002 application in the proposed total gallons per week that would be
trucked from the springs to the bottling facility.
8.
To address the effect of the increase of truck trips on neighborhood
traffic, Appellee-Applicant proposed running a significant number of the truck
trips at night when fewer residents use
9.
Testimony at the public hearings and evidence from the record show that
the use of smaller trucks, either the 4,200-gallon trucks proposed by
Appellee-Applicant or the 5,000-gallon trucks referred to in Appellants’ traffic
report, may improve safety on Rogers Road, though that increase in safety may be
offset somewhat by a corresponding increase in number of truck trips due to the
use of smaller, single-bodied trucks.
10. A
significant amount of testimony was offered at the public hearings in opposition
to Appellee-Applicant’s proposed nighttime trucking hours. This testimony established that
nighttime trucking is not typical of the character of the area near
Appellee-Applicant’s springs.
Testimony further demonstrated that Appellee-Applicant’s neighbors would
prefer that the trucks operate during the day because daytime traffic is more
reasonable, see Testimony of Richard Osborn, Aug. 19, 2003 Hearing, Tape 1, Side
A, at 650–60,[5]
because “everyone has traffic during the day,” Testimony of Robert White, July
17, 2003 Hearing, Tape 2, Side B, at 243, and because people “expect a certain
amount of traffic during daylight hours,” id. Side A, at
923–44.
11. Rogers Road
varies in width from eighteen to twenty-two feet as one travels northerly from
Route 66. However, that stretch of
the road is also relatively straight and flat, with the exception of a ninety
degree turn to the east immediately after Appellee-Applicant’s access drive,
which is also at the foot of a short but steep grade. Appellee-Applicant proposes some minor
changes to the access drive in order for it to remain stable, but those changes
are not related to its general design, nor do they affect the drive’s
intersection with
12. The DRB
determined that truck traffic on
13. Some
testimony was offered to the DRB that
14.
Notwithstanding mud season conditions typical of many unpaved roads in
15. In 1973
there were only two residences on
16. After three
public hearings on the record on June 17, July 17, and August 19, 2003, the
Town’s DRB closed public hearings, held a deliberative session, and then
approved Appellee-Applicant’s site plan and conditional use permit expansion,
with conditions, on October 15, 2003.
Discussion
Appellants first question whether
Appellee-Applicant’s spring water development can properly and constitutionally
be considered as an extension of its previously granted 1993 conditional use
permit. At the outset, we note that
this Court previously upheld the Town DRB’s decision to treat
Appellee-Applicant’s previous application as an amendment to the 1993
conditional use permit. See
Appeal of Walters, et al., Docket No. 234-10-02 Vtec
(
The Court’s reasoning regarding
Appellee-Applicant’s prior similar application for the same property is
persuasive here, as the present application does not propose adding a new use,
nor does it propose a change in use.
The additional spring development proposed is neither a use not
specifically permitted under Regulations § 2.4.3, nor is it an expansion of a
non-conforming use under Regulations § 2.5.4. Rather, it is an application to amend
the 1993 conditional use permit.
Appellee-Applicant’s 1993 conditional use permit is still valid, and
although Appellee-Applicant’s spring water production use is not specifically
enumerated in the Regulations, the DRB was correct in not reevaluating the use
because the 1993 permit was not appealed and therefore its validity cannot be
challenged, directly or indirectly, in this proceeding.
Moreover, Appellee-Applicant’s
present application cannot be considered as an expansion of a non-conforming use
under Regulations § 2.5.4 because the use satisfies neither the Regulations’
definition of a “non-conforming use” contained in § 1.3.42, nor the applicable
statutory definition in 24 V.S.A. § 4408(a)(1) (2003). Appellee-Applicant’s use is not
non-conforming under the Regulations because it did not legally exist upon the
effective date of the Regulations pertaining to that use,
Appellants next contest the condition
on Appellee-Applicant’s permit regarding the applicable truck size for hauling
spring water from the
In an on-the-record appeal, the
factual findings of the administrative body are given great weight, although
they are not immune from scrutiny.
The court must determine if substantial evidence exists in the record as
a whole from which the factual findings of the DRB might reasonably be
inferred. See In re Petition of
Town of
In reviewing the record from the DRB,
we find substantial evidence in the record as a whole to justify the DRB’s
imposition of a condition limiting the use of trucks to those with no more than
5,000 gallons of storage. In this
instance, there is no conflicting evidence on this point. Since the only evidence pertaining to
the size of trucks presented at the hearings related to single-bodied trucks
with either 4,200 or 5,000-gallon capacity, we find the DRB’s condition
regarding truck capacity reasonable and adequately supported by the record. While Appellee-Applicant, through their
representative Jack Baker, only testified to using 4,200-gallon trucks to
transport water from the Rogers Road springs to the bottling plant, Appellants’
own traffic study, prepared by Trudell Consulting Engineers, Inc., refers
specifically to Appellee-Applicant using either “4,200 or 5,000-gallon single
unit trucks.” See Attach. 2 to
Appellee’s Mem. in Opp’n to Mot. for Summ. J., at 1; see also DRB Ex. O, at
1.
On
Because this is an application to
amend a conditional use permit, 24 V.S.A. § 4407(2) allows the DRB to “attach
such additional reasonable conditions and safeguards as it may deem necessary to
implement the purposes of this chapter and the zoning regulations.”
Appellants also allege that the DRB
erred in approving hours different from those Appellee-Applicant proposed in its
application. Appellant further
argues that the evidence presented regarding the trucks’ hours of operation was
not substantial enough to support the DRB’s conclusion that Appellee-Applicant’s
trucks should only run from
The record reveals that
Appellee-Applicant’s representatives, apparently believing that they were
responding to the wishes of the neighbors, initially proposed operating the
water hauling trucks at times other than when Rogers Road was used most
frequently by neighbors: from 6:00 A.M. to 8:00 A.M. and from 3:00 P.M. to 6:00
P.M. Following this logic,
Applicant initially proposed running trucks from 8:00 A.M.–3:00 P.M and from
6:00 P.M.–6:00 A.M. Monday-Friday; all day Saturday to 6:00 A.M. Sunday morning;
and from 8:00 P.M. Sunday night to 6:00 A.M. Monday. The error in this logic became very
apparent at the DRB hearings, where several residents appeared to protest
Appellee-Applicant’s proposed nighttime trucking operations, alleging among
other things that nighttime trucking created a significant disturbance and was
contrary to the character of the area.
The notable opposition to the
nighttime trucking regime and the considerable evidence relating to the
neighbors’ expectations of daytime trucking activities provide ample support for
the permit condition prohibiting trucking after 9:00 P.M and limiting
Appellee-Applicant’s trucking to operational hours other than in the middle of
the night. Testimony at the hearing
established that nighttime trucking would have an adverse effect on the
character of the area, see DRB hearing tapes of June 17, 2003, tape 1, side A at
872; July 17, 2003, tape 2, side A, at 923–44, side B, at 243; August 19, 2003,
tape 2, side A, at 814–end, and demonstrated that residents of Randolph Center
along the trucking route from the Rogers Road springs to the bottling plant
preferred traffic during hours that would not disrupt their sleeping. See DRB hearing tapes of July 17, 2003,
tape 2, side A, at 923–44 (in particular, Robert White stated that people
“expect a certain amount of traffic during daylight hours.”); tape 2, side B, at
243; August 19, 2003, tape 1, side B, at 506, 650–60, 675; tape 3, side A, at
125.
While substantial evidence was
presented in opposition to the proposed nighttime trucking, substantial evidence
also indicated that Appellee-Applicant’s trucks when run during daytime hours
are part of the character of the area.
Therefore, we find that the condition limiting Appellee-Applicant’s
trucking hours is reasonable under 24 V.S.A. § 4407. There is substantial evidentiary support
for the trucking hours incorporated into Appellee-Applicant’s amended
conditional use permit.
The language of 24 V.S.A. § 1204 also
does not support Appellants’ argument that the section requires the notice of a
hearing to state the specific subject matter of the testimony (as opposed to the
subject of the hearing generally) and the specific witness who will be
testifying at the hearing. The
plain meaning of that unambiguous section of the Municipal Administrative
Procedures Act is that the notice of a hearing only requires notice of an
opportunity for all interested persons to be heard, and compliance with 24
V.S.A. § 4447, which requires that notice “be given not less than 15 days prior
to the date of hearing” by the methods enumerated in that section. 24 V.S.A. §§ 1204(a), 4447(a). As long as all parties have an
opportunity “to respond and present evidence and argument on all issues
involved,” the notice provision is satisfied.
Accordingly, based on the foregoing,
it is hereby ordered and adjudged that Appellants’ motion for summary judgment
is DENIED; Appellee-Applicant’s motion for summary judgment is GRANTED. The DRB’s decision on
Appellee-Applicant’s amended site plan and conditional use permit is AFFIRMED,
as all conditions specifically challenged by Appellants in their pending motion
are supported by substantial evidence in the record.
The Court believes that it has
addressed all issues presented for consideration by the parties’ pending
motions, but is also aware that certain issues presented in Appellants’
Statement of Questions may not have been addressed. In that regard, Appellants are to submit
within thirty (30) days (i.e.: no later than
Done at
Thomas S. Durkin, Environmental Judge
[1] Due to the sale of Vermont Pure Springs,
Inc., this Court authorized the substitution of Micropack Corporation as the
named Appellee-Applicant by Entry Order of
[2] The parties have filed motions for summary judgment and memoranda opposing each other’s motions. Summary judgment may be a misleading label for such pleadings in an “on the record” proceeding, as there is no “trial” or taking of new evidence. However, until a better practice is developed and authorized by our Rules, summary judgment motions are the most effective vehicle to present the disputed legal issues to the Court.
[3] The record in this appeal includes
Appellee-Applicant’s application of
[4] The DRB Decision was first issued on
[5] While reviewing the recordings of the DRB hearings on audio cassette, it came to the Court’s attention that different cassette players’ counters count at different rates. The Court is using the counter readings from its cassette player, and these specific numerical references may or may not correspond to those of other cassette players.
[6] If Appellee-Applicant’s application were considered under the new state statute, amended by An Act Relating to Consolidated Environmental Appeals and Revisions of Land Use Development Law, 2004, No. 115 (Adj. Sess.), Appellee-Applicant’s application might be considered under the non-conformities provisions, but we do not reach that determination here. See 24 V.S.A. § 4303(15) (2004) (stating that non-conforming uses include “a use improperly authorized as a result of error by the administrative officer.”)