STATE OF VERMONT
ENVIRONMENTAL COURT
}
Appeals
of Harrison
}
Docket Nos. 110-6-04 Vtec and 44-2-05 Vtec
}
}
Decision and Order on Motion for Summary
Judgment
Appellant-Applicants
James and Janet Harrison (Appellants) appeal from decisions of the Development
Review Board (DRB) of the Town of Berkshire concerning Appellants=
proposed Planned Residential Development (PRD) subdivision. In Docket No. 110-6-04 Vtec, Appellants
appealed from the DRB=s
May 20, 2004 refusal to accept Appellants=
application for site plan review and for approval of the subdivision[1]
as a PRD. In Docket No. 44-2-05
Vtec, Appellants appealed from a January 27, 2005 decision of the DRB denying
Appellants=
application for site plan approval and for approval of the subdivision as a
PRD. Appellants are represented by
Eric A. Poehlmann, Esq.; the Town is represented Robert E. Farrar, Esq.
Appellants
moved for summary judgment on the issue of whether any of their site plans
should be deemed to be approved, based on the sequence of applications and DRB
actions in these matters, including whether or when any of their applications
should have been accepted as complete.
The following facts are undisputed unless otherwise noted.
Appellants
own an approximately 77.7-acre parcel of land located off Route 108, in the
Rural Lands zoning district of the Town of Berkshire. The parties have not provided either the
application or the proposed site plan at issue in the present appeals, but if
the parcel is the same land as was at issue in an earlier appeal before the
Environmental Court, Docket No. 199-9-02 Vtec, it consists of land located to
the rear of four existing lots along Route 108, with access to Route 108 via a
50-foot-wide easement (right-of-way) proposed as a private road. In the present appeals, Appellants
propose to subdivide a 25.1-acre portion of that 77.7-acre parcel into six[2]
lots as a PRD.
Appellants
first submitted an application for site plan[3]
review on December 29, 2003, which was initially considered by the DRB at its
January 15, 2004 hearing. Based on
the unsigned minutes of that hearing, at the hearing Appellants=
engineer presented the DRB with two other documents, described in the minutes as
a ARequest
for Waiver of Subdivision standards@
(presumably under the PRD regulations in '245,
which provide for such a request) and a ARequest
for Site Plan Review.@ The minutes state that the DRB voted to
A[w]ait
for Act 250 process to be completed before the DRB accepts this proposal for
official review.@ Appellants did not appeal this action of
the DRB; therefore Questions 1 and
2 in the Statement of Questions in Docket No. 110-6-04 Vtec are beyond the scope
of this appeal and are HEREBY DISMISSED.
Rather,
Appellants submitted updated information in support of their site plan
application at the DRB=s
hearing on May 20, 2004. Based on
the unsigned minutes of that hearing, at the hearing the DRB again decided
Anot
to hear [the] proposal at this time, that way the clock will not
start,@
and the DRB chairman stated that the ABoard
will not accept [the] site plan application at this time because as previously
voted the Board would not review [it] until [an] Act 250 permit was
approved.@ On June 18, 2004, Appellants appealed to
this Court from all Adecisions,
actions and refusals to act@
taken by the DRB at its May 20, 2004 hearing, that is, the DRB=s
refusal to Aaccept@
or Ahear@
Appellants=
site plan application. That appeal
was assigned Docket No. 110-6-04 Vtec; Questions 3 and 4 of the Statement of
Questions, pertaining to those actions taken by the DRB at the May 20, 2004
hearing, remain in the appeal.
On
June 29, 2004, the Chairperson of the Town=s
Selectboard sent a letter to Appellants stating that the Selectboard had
directed the DRB to proceed with the review of Appellants=
proposed PRD subdivision. The
letter informed them that a DRB meeting would be held on July 15, 2004, at which
time Appellants=
application would be on the agenda.
Based
on the unsigned and unapproved minutes of the DRB=s
July 15, 2004 hearing, at that
hearing Appellants=
engineer Apresented
a request for Site Plan Review@
for the proposed PRD, presumably
including the elements for which waiver was being requested as a PRD,
under ''235
and 245 of the Zoning Bylaws. Later
in the meeting, the DRB Areviewed
the Zoning Bylaws and compiled a tent[at]ive list of additional information
needed to consider the Harrison request.@ The DRB scheduled a Aspecial
meeting@
for July 29, 2004 at 7:00 p.m. at the Berkshire Town Office, Ato
conclude the list of additional information needed to consider the Harrison
request,@
and also scheduled its next regular meeting for August 19, 2004.
If
the July 29, 2004 special meeting took place, or was further recessed to August
19, 2004, no minutes of it have been provided to the Court. However, it appears that
Appellants=
engineer must have been informed of the additional information requested by the
DRB at some time before the August 19, 2004 regular meeting, as at that meeting
he attended, presented Aupdated
drawings@
and a Asoil
evaluation,@
and gave Adetailed
answers@
to a list of questions prepared by the Chairman of the DRB, who was not present
at the August 19 hearing. Based on
the unsigned minutes of that hearing, six individuals: Kimberly Ransom, Harold
Greenia, Ronald Wonot, Jacqueline Greenia, Lorraine Conlon and Patrick Heaghney,
referred to as interested parties and as neighboring landowners, were also
provided the opportunity ask questions regarding the
proposal.
At
the close of the August 19, 2004 meeting, the three members of the DRB who were
present voted Anot
to accept the application . . . at this time because the Chairman was not
present and he had made all the legal contacts concerning the
application.@ The DRB then voted to Arecess
the meetingA
until September 2, 2004.
However, if a September 2, 2004 meeting took place, or was further
recessed to September 16, 2004, no minutes of it have been provided to the
Court.
On September 16, 2004, the DRB held another hearing. Based on the unsigned and
unapproved minutes of the September 16, 2004 hearing, Appellants=
engineer requested that Atonight=s
meeting be considered informal pending the September 27th, 2004 environmental
court date, [as Appellants] do not want the information discussed tonight to
prejudice the case.@ The minutes state that
Appellants=
engineer Asubmitted
revised copies of the [site] plan and informational sheets to be
reviewed,@
that Adiscussion
was held about the revisions,@
and that Appellants=
engineer Awould
be back for the October 21st, 2004 meeting depending on the outcome of the
September 27th, 2004 court@
hearing. The DRB voted to adjourn
the meeting, without reference to another date.
This
Court held pretrial conferences regarding the then-pending appeal (Docket No.
110-6-04 Vtec) on September 27 and 28, 2004, at which the parties agreed that
the Court would place the appeal on
inactive status until the DRB would have reached a decision on the merits of
Appellants=
site plan application, preserving whatever deemed-approval or other arguments
Appellants had as of that date in that appeal.
DRB
hearings on the merits of Appellants=
site plan and PRD subdivision application were held on October 28, 2004,
November 18, 2004, and December 16, 2004, as referred to in the January 27, 2005
DRB decision. That decision states
that the DRB Aelected
to review the application on October 28, 2004,@
and again that it Avoted
unanimously to accept the Site Plan for review on October 28, 2004.@
Based
on the unsigned and unapproved minutes of the December 16, 2004 hearing, it was
at that hearing that the DRB voted to deny Appellants=
application on its merits, on the basis of its failure to Ameet
the minimum road frontage.@ The written decision was issued on
January 27, 2005; its appeal to this Court was assigned Docket No. 44-2-05
Vtec.
Completeness
and deemed-approval issues in Docket No. 110-6-04 Vtec
In
the decision appealed in Docket No. 110-6-04 Vtec, the DRB initially refused to
accept Applicants=
applications for site plan approval, apparently on the grounds that the
applications did not include an issued Act 250 permit. (We will assume, for the purposes of
this discussion, that this project does require Act 250 approval, as this issue
would be moot if it does not.)
The
final step in approval of any project is a zoning permit issued by the Zoning
Administrator. Section 215(b)(1) of
the Zoning Bylaws provides that no zoning permit shall be issued unless and
until the listed other permits and approvals have been issued, if those other
permits and approvals are required for the project. Section 215(b)(1) specifically lists
Asite
plan approval, if applicable,@
'215(b)(1)(B),
as one prerequisite to issuance of a zoning permit, and also lists Aall
applicable state permits,@
'215(b)(1)(E),
as another prerequisite to issuance of a zoning permit. Thus the Zoning Administrator would not
be authorized to issue a zoning permit until a project=s
Act 250 permit was in place and until the project had received site plan
approval from the DRB.
However,
nothing in '215(b)(1)
requires an applicant to obtain the various other permits and approvals required
for a project in any particular order, prior to applying for the zoning
permit. Section 215(b)(1) does
require that an Act 250 permit be obtained for the project prior to issuance of
a zoning permit by the Zoning Administrator, but it does not require that the
Act 250 permit be obtained prior to site plan approval (or prior to approval of
the project as a PRD subdivision).
By
contrast, nothing in '235
refers to any required state permits as a prerequisite to the DRB=s
consideration of site plan approval.
Unlike the prerequisites to zoning permit approval in '215(b)(1)(E), '235
only requires information pertaining to site plan issues to be included in the
application for site plan approval, '235(c)(1)
(as well as requiring submittal of the site plan drawings required by
'235(c)(2)). The requirement in '235(c)(1)(F)
that the site plan application=s
written statement include Aevidence
of receipt of all necessary reviews, approvals, and permits@
therefore must refer only to the reviews and approvals necessary for site plan
approval (including subdivision and PRD approval conducted through site plan
approval), such as the municipal or state approval of septic systems required by
'240(a)(3). As nothing in ''235,
240 or 245 requires prior Act 250 approval in order to obtain site plan
approval, the DRB should not have
refused to consider the site plan application on the sole basis that the project
had not yet obtained its Act 250 permit.
However, under the specific language in '235(f)
of the Zoning Bylaws, Appellants were not then entitled to deemed approval as to
the application submitted at the May 2004 DRB hearing. That section requires that, within sixty
days of Areceiving
a complete site plan application@
the DRB shall Aissue
a written statement on the application;@
it also provides that failure Ato
render a decision@
shall be deemed approval of the application.
Analyzed under '235(f),
the DRB did not consider the May 20, 2004 site plan application to be complete
until, at the earliest, the August 19, 2004 meeting, as the DRB required more
information (for reasons other than the Act 250 permit) through July 15, 2004,
which Appellants provided at the August 19, 2004 hearing. As of September 28, 2004, the parties
agreed to stop the clock. As of
that date, the DRB had used 40 days, and therefore deemed approval did not
occur. When the clock started again
on October 28, 2004, that date was treated by the DRB as the date of acceptance
of a newly-revised application. The
deemed-approval arguments regarding the application accepted for review on
October 28, 2004, are discussed below under Docket No. 44-2-05
Vtec.
The
DRB=s
failure to consider the merits of the May 20, 2004 application would have
required us to remand this matter to the DRB for it to consider that application
on its merits or to rule on its lack of completeness on other grounds. However, as the DRB proceeded in June of
2004 to consider the application on its merits without regard to the Act 250
permit issue, a remand is unnecessary.
Deemed-approval
issues in Docket No. 44-2-05 Vtec
Section
235(f) of the Zoning Bylaws requires that, within sixty days of Areceiving
a complete site plan application@
the DRB shall Aissue
a written statement on the application;@
it also provides that failure Ato
render a decision@
shall be deemed approval of the application. In this respect it goes beyond the state
statute[4]
in effect in early 2004, which required the DRB to Aact
to approve or disapprove@
the site plan within sixty days after the date upon which it Areceives
the proposed plan.@ 24 V.S.A. former '4407(5). That is, the state statute had no
completeness requirement for the application.
The
DRB also seems to have confused the trigger for the start of the deemed-approval
period for site plan approval with that for other types of DRB actions. The site plan approval deemed-approval
period is triggered by the DRB=s
receipt of a complete application.
The clock starts ticking once the application is complete; it cannot be
postponed by recessing the hearing from time to time. By contrast, under the state statute
(applicable as there is no specific deemed-approval provision in the Zoning
Bylaws regarding these other proceedings), the deemed-approval periods for
subdivision approval, conditional use approval, or other appeals to the DRB are
triggered from the date of the Apublic
hearing,@
the date of the Afinal@
public hearing, or from Acompleting@
the hearing. 24 V.S.A. former
''4415,
4407(2), and 4470(a), respectively.
While
the state statute changed as of July 1, 2004, under 24 V.S.A. '4481,
existing municipal bylaws that are inconsistent with the new statute were not
superseded by the state statute until September 1, 2005, and then only to the
extent that they may be inconsistent with changes found in sections codified as
24 V.S.A ''4412,
4413, and 4440 through 4476 of the new statute. Thus, even if the changes in the deemed
approval provisions[5]
of the state statute are considered to have superseded '235(f)
of the Zoning Bylaws, that would not have occurred until September 1, 2005,
after the events at issue in both appeals.
In
Docket No. 44-2-05 Vtec, the application was accepted for review on October 28,
2004, and may have been[6]
determined to be complete[7]
at that meeting. The DRB rendered
its decision, for the purposes of deemed approval, on December 16, 2004, when it
voted to deny the application, 49 days later. See, e.g., Appeal of
Griffin, Docket No. 92-6-04 Vtec (Vt. Envtl. Ct., May 23, 2005), at 7 (ZBA
Arendered
its decision@when
it voted).
The
DRB then completed the requirements of '235(f)
by issuing a written decision. The
January 27, 2005 written decision was not issued within the sixty-day time
period from October 28, 2004.
However, '235(f)
does not provide the deemed-approval remedy for failure to issue the
Awritten
statement on the decision@
within sixty days; rather, deemed approval is only triggered by failure to
Arender
the decision@
within the sixty-day period. Deemed
approval is intended to remedy protracted deliberations and indecision of the
DRB, In re Appeal of McEwing
Services, LLC, 2004 VT 53, &
21, but is not to be used beyond that purpose, Appeal of Newton
Enterprises, 167 Vt. 459, 464-65 (1998). The decision was rendered within the
required time period. Therefore,
deemed approval of the October 28, 2004 site plan application did not occur and
Appellants=
motion for summary judgment on Questions 1 and 2 in Docket No. 44-2-05 Vtec must be
denied.
Accordingly,
based on the foregoing, it is hereby ORDERED and ADJUDGED in Docket No. 110-6-04
Vtec that Questions 1 and 2 of the Statement of Questions are DISMISSED as
beyond the scope of the appeal from actions taken by the DRB on May 20,
2004. Appellants=
Motion for Summary Judgment is GRANTED as to Question 3 of the Statement of
Questions, in that lack of prior Act 250 approval for the project does not in
and of itself render a site plan application incomplete; but
Appellants=
Motion for Summary Judgment is DENIED and Summary Judgment is GRANTED in favor
of the Town as to Question 4 of the Statement of Questions, in that
Appellants=
site plan application made on May 20, 2004, does not qualify for deemed approval
under '235(f)
of the Zoning Bylaws. This decision
concludes Docket No. 110-6-04 Vtec.
Also
based on the foregoing, it is hereby ORDERED and ADJUDGED in Docket No. 44-2-05
Vtec that Appellants=
Motion for Summary Judgment is DENIED as to Questions 1 and 2 of the Statement
of Questions. A conference is
hereby scheduled for December 12, 2005, (see enclosed notice) to discuss the
remaining issues in Questions 3, 4, and 5 of the Statement of Questions in
Docket No. 44-2-05 Vtec. The
parties should be prepared to discuss whether the proposal must be considered
under ''235,
240 and 245 of the Zoning Bylaws; to state which elements they request waivers
for as a PRD subdivision; and to file a copy of the site plan prior to the
conference.
Done
at Berlin, Vermont, this 29th day of November,
2005.
_________________________________________________
Merideth
Wright
Environmental
Judge
[1] Under the Berkshire Zoning Bylaws,
approval of a subdivision under '240
is accomplished through site plan review ('235)
rather than as a separate proceeding, as is approval of modifications for a PRD
under '245.
[2] Because the Court was not provided with
the site plan, we cannot determine why the application is not in fact a
seven-lot PRD subdivision, consisting of the six described lots plus a
seventh lot containing the 52.6 remaining acres retained by Appellants. However, the issues raised in this
appeal do not depend upon that distinction.
[3] The Berkshire Zoning Bylaws do not in
fact provide for separate Apreliminary@
and Afinal@
stages of site plan review, although the parties have referred to the December
2003 application as one for Apreliminary@
site plan approval, and to the revised application submitted in May 2004 as one
for Afinal@
site plan approval.
[4] The state statute in effect through June
of 2004 provided a 60-day deemed-approval period for a Planning
Commission=s
or DRB=s
actions on site plan review, counted from the date on which it Areceives
the proposed plan.@ 24 V.S.A. former '4407(5). The statute provided a 45-day
deemed-approval period for a Planning Commission=s
or DRB=s
actions on approval of a subdivision, counted from the date of Athe
public hearing.@ 24 V.S.A. former '4415. (Compare the 60-day deemed-approval
period for a Zoning Board of Adjustment=s
(ZBA=s)
or DRB=s
actions on conditional uses, counted from the Afinal
public hearing,@
24 V.S.A. former 4407(2); and the 45-day deemed-approval period for all other
matters appealed to the ZBA or DRB, counted from Acompleting@
the hearing. 24 V.S.A. former
''4464(c)and
4470(a).)
[5] See 24 V.S.A. '4464(b)(1)
(2004) (45-day deemed-approval period applicable to all municipal decisions,
counted from the Aadjournment@
of the hearing):
The
appropriate municipal panel may recess the proceedings on any application
pending submission of additional information. The panel should close the evidence
promptly after all parties have submitted the requested information. The panel shall adjourn the hearing and
issue a decision within 45 days after the adjournment of the hearing, and
failure of the appropriate municipal panel to issue a decision within this
period shall be deemed approval and shall be effective on the 46th
day.
[6] The October and November 2004 DRB
meetings were not transcribed, nor were even unofficial minutes prepared for
those meetings, due to technical problems with the recording
equipment.
[7] In addition, at the December 16, 2004
hearing, Appellants submitted Aa
new landscaping plan [and] soil data sheets;@
Appellants themselves characterize these materials as having been submitted
Aat
the DRB=s
insistence,@
suggesting that the DRB may instead have viewed the application as incomplete
until that time. See
Appellants=
Reply to the Town=s
Resp. to Appellants=
Mot. for Summ. J., at 2. While
under In re McEwing Services, LLC, 2004 VT 53, at &
19, the Aunsolicited,
voluntary submission of evidence after the deemed approval period has
run@
does not bar the application of the deemed approval remedy, if the submission of
supplemental information were in fact requested by the DRB, it would not fall
within this rule.