STATE
OF
ENVIRONMENTAL
COURT
}
In
re: Mountainside Properties, Inc. } Docket No. 117-6-05
Vtec
Land
Use Permit Amendment
}
(Appeal
of Wilbanks & Flocken)
}
Decision
and Order on Cross-Motions for Summary Judgment
Appellants George Wilbanks and Ann Flocken appeal from the decision of
the District Environmental Commission #1 granting Appellee-Applicant
Mountainside Properties, Inc.’s application to amend Act 250 Land Use Permit
#1R0468-16 by adding a new single-family house lot and reconfiguring two other
single-family house lots within a 31.96-acre parcel southerly of East Mountain
Road (formerly known as Roaring Brook East Road) near the Highridge Condominiums
in the Town of Killington.
Appellants are represented by Charles F. Storrow, Esq.;
Appellee-Applicant is represented by C. Daniel Hershenson,
Esq.
Both parties have filed cross-motions for summary judgment on two of the
three issues presented by Appellants’ Statement of Questions, summarized as
follows:
(a).
Whether Appellee-Applicant’s request to amend its Act 250 permit should
be denied under Environmental Board Rule 34(E) or the so-called Stowe Club
Highlands analysis; and
(b).
Whether Appellee-Applicant’s application to amend its Act 250 permit
should be denied on the basis of the need for finality.
Factual
Background
The following facts are undisputed unless otherwise
noted:
1.
On June 30, 1989, Appellee-Applicant joined in an application for an Act
250 permit to develop a 31.96-acre parcel of land above an elevation of 2,100
feet and southerly of East Mountain Road (formerly known as Roaring Brook East
Road) and the Highridge Condominiums in the Town of Killington, then known as
the Town of Sherburne.
Appellee-Applicant proposed to create thirteen subdivided lots, as well
as associated utilities, roads, and recreational facilities, as part of a
larger, previously-approved 400-acre planned unit development. This portion of the development is known
as the Mountainside subdivision.
The first Act 250 land use permit application solely relating to the
Mountainside subdivision was assigned the docket number of
1R0468-15.
2.
On August 1, 1990, District Environmental Commission #1 (District
Commission) issued Act 250 permit #1R0468-15A (the 1990 permit) for the first
phase of the Mountainside subdivision, including two single-family house lots,
numbered Lots 1 and 14, utilities, a project road as far as Lot 1, and a
primitive well access road as far as future Lot 12A. The remainder of the lots were to be
developed in the proposed second phase of the project, after Appellee-Applicant
relocated the neighboring Highridge Condominiums’ well, since the well
protection zone would be encroached upon by the proposed Mountainside Lots 2
through 13.
3.
On
4.
Shortly thereafter, on
5.
After the relocation of Highridge Condominiums’ well, the District
Commission held additional hearings on the remainder of the Mountainside
subdivision. Appellee-Applicant
submitted plans for fourteen single-family house lots, including the above
referenced plat map with a 3,500-foot road, tennis courts, and related
utilities. The District Commission
approved this application on
6.
Two of the conditions of the 1992 permit required
that:
This
project shall be completed in accordance with the Findings of Fact, Conclusions
of Law, and Order #1R0468-15, and in accordance with plans and exhibits stamped
“Approved” and on file with the District Environmental Commission. In the event of any conflict, the terms
and conditions of this permit and the facts relied upon in the Findings of Fact
and Conclusions of Law shall supersede the approved plans and
exhibits.
Attach.
to Appellee-Applicant’s Mot. for Summ. J., Ex. 2, at 2 (Condition No. 6, Act 250
Land Use Permit #1R0468-15).
All
road and utility construction and site work associated with this project shall
be completed in accordance with the approved plans by
Attach.
to Appellee-Applicant’s Mot. for Summ. J., Ex. 2, at 3 (Condition No. 18, Act
250 Land Use Permit #1R0468-15).
7.
Appellee-Applicant submitted numerous exhibits in support of its
application for the 1992 permit, including site plans depicting all fourteen
building lots, ranging in size from one-half acre (Lot 11) to 1.3 acres (Lot 1),
including 21.56 acres outside the housing lots. Attach. to Appellants’ Mot. for Summ.
J., Ex. E. Another site plan
submitted in connection with the 1992 permit application proposed to locate four
tennis courts, a paddle tennis court, and related shelters on an area
northeasterly of housing
8.
These recreation facilities were proposed for land designated on the
recorded plat layout as both “Common Land” and “Reserved No. 2.” The recreation facilities were proposed
to be located on the 14,000 square-foot rectangular “Common Land” extension from
the proposed cul-de-sac and on “Reserved No. 2” to the south and east of the
14,000 square-foot area of common land.
9.
On
10.
On
11.
Among the standard conditions of the 1994 permit were that the project be
completed in accordance with the plans submitted with the application for an
amended permit; that all terms and conditions of the original permit remained in
effect, except as modified; and that “all road and utility construction and site
work” be completed by October 15, 1995, unless an extension is granted by the
District Commission. See Attach. to
Appellee-Applicant’s Mot. for Summ. J., Ex. 4, at 2.
12.
In January 2004, Appellants purchased
13.
On
14.
On
15.
After public hearings on Appellee-Applicant’s proposal, the District
Commission reviewed the permit amendment application under Act 250 Criteria 1B,
2, 3, and 8, pursuant to 10 V.S.A. § 6086(a)(1)(B), (2), (3), (8), and issued
its Findings, granting the requested permit amendment (#1R0468-17) on June 15,
2005.
16.
Appellants timely filed their Notice of Appeal with this Court of the
Permit and Findings issued by the District Commission.
Discussion
Appellants contend that Appellee-Applicant’s permit amendment proposal to
reconfigure two lots and to add an additional lot to the Mountainside
subdivision should be denied because the land to the east and south of
Until
now, the Environmental Court has not had the opportunity to consider issues
related to Act 250 permit amendments in light of the Court’s new jurisdiction
over appeals from district commissions, pursuant to 10 V.S.A. § 8504
(2004). In these de
novo proceedings, the legislature has directed us to apply the
“substantive standards” that were applicable to the tribunal appealed from and
to give equal weight to prior decisions of the former Environmental Board
(Board) as we would our own prior decisions. 10 V.S.A. § 8504(h),
(m).
At
the outset, we note that this Court has its own procedural rules, the Vermont
Rules for Environmental Court Proceedings, that have been specifically
promulgated by the Vermont Supreme Court.
Therefore we are bound to employ the substantive standards applicable
when the District Commission heard this application, while also continuing to
adhere to our own procedural rules.
Pursuant
to the Vermont Supreme Court’s directive, the Board used its statutory authority
to draft and promulgate Rule 34(E),[1]
a Rule that we now regard as one of the substantive standards that this Court is
charged with applying in the Act 250 context.
Appellants
argue that EBR 34(E) applies to Appellee-Applicant’s proposed amendment of the
Mountainside subdivision because Appellee-Applicant requested an amendment of
conditions requiring compliance with plans submitted in the course of the permit
application process and requiring that construction be completed by a certain
date. Rule 34(E) governs the
amendment of “critical” Act 250 permit conditions. We conclude that EBR 34(E), by its
language, is not applicable here.
Appellee-Applicant
does not seek an amendment to any condition of its previous permits. Rather, Appellee-Applicant seeks to
amend the development’s layout and site plans, which are not specific permit
conditions, despite being referenced in the Act 250 permits. The language of EBR 34(E) is clear,
“This rule governs applications to amend permit conditions which were included
to resolve issues critical to the district commission’s or the board’s issuance
of prior permits pursuant to the criteria of 10 V.S.A. § 6086(a).” EBR 34(E)(1).
Appellants’
reference to the terms of the previous permits that require further review by
the District Commission, should the Permittee wish to deviate from the approved
plans, and Appellants’ characterization of these terms as critical permit
conditions invoking Rule 34(E) review is unpersuasive and not supported by prior
Board precedent. We have found no
prior Board decision that characterizes such terms (Appellee-Applicant refers to
such terms as “boilerplate”) as critical, at least within the context of a Rule
34(E) review. Such terms reinforce
an important constant in state land use permitting—Act 250 permits allow a
property owner to conduct the improvements specifically authorized by the
permit, but no more than that. When
property owners wish to complete further improvements to a property already
subject to an Act 250 permit, they may be allowed to do so only after submitting
the proposed improvements in a permit amendment application. If we were to determine that these
necessary terms, included in all Act 250 permits, were “critical permit
conditions” for purposes of Rule 34(E), there would be no distinction left to
the initial analysis under that Rule of whether a permit condition were
“critical.” We cannot disregard an
analysis made necessary by the specific language of this Rule. 10 V.S.A. § 8504(h) directs that we apply
this substantive standard.
We
now turn to the Appellants’ next argument as to why Appellee-Applicant’s
proposed permit amendment application should be denied.[2] Appellants assert that
Appellee-Applicant should be bound by the conditions of its 1994 permit,
requiring “all road and utility construction and site work” to be completed by
October 15, 1995, and that the construction be completed in accordance with the
District Commission Findings, as well as all the exhibits approved by the
District Commission. They further
argue that the Commission relied on these conditions to ensure that the
Mountainside subdivision would continue to meet the applicable Act 250
criteria.
In
deciding whether to allow an amendment to an Act 250 land use permit, “the
central question . . . is not whether to give effect to the original permit
conditions, but under what circumstances those permit conditions may be
modified.”
While
the original permit process should not merely be “a prologue to continued
applications for permit amendments,” Stowe Club Highlands, 166
Appellants
also argue that the 1992 permit requires the tennis courts and other
recreational facilities to be placed on the land to the east and south of their
property,
Another
factor when considering the need for finality in the permit process is the
reliance on permits and their conditions by abutting landowners and other
parties, including successors in title. Appellants argue that in purchasing Lot
1, they were reasonable in relying on their transactional attorney’s
representation that it did not appear that anything was planned to be built on
the land to the east and south of their property, with the possible exception of
proposed tennis courts and other recreation facilities.
Reviewing
the recorded site plan and Appellee-Applicant’s previously-granted permits, we
conclude that the reliance Appellants represent here was unreasonable. As stated above, nothing in
Appellee-Applicant’s prior Act 250 permits required the tennis courts and
recreation facilities to be placed specifically to the east and south of
Appellants’ lot. The recorded site
plans were also devoid of any language or representation that the tennis courts
would be constructed in a specific area to the east and south of
The
above considerations do not weigh heavily in favor of the finality of
Appellee-Applicant’s permit.
However, we still must balance the need for finality against the need for
flexibility in the permit process.
If
we are to import a condition, retroactively, that would restrict future
development, we could do so only if there were other indications that such
importation was intended. Such
indications could include a dedication of all “reserved” and “common” land as
“Common Property,” pursuant to the subdivision’s Declaration of Protective
Covenants or a conveyance of all or some fractional interest in the “common” or
“reserved” property. However, in
the present case, there is no evidence of such conveyances.[5] Also, the previously-granted Act 250
permits predicted that the Mountainside subdivision project might be amended,
since the District Commission incorporated into those permits a method for
Appellee-Applicant to apply for an amendment. See Attach. to Appellee-Applicant’s Mot.
for Summ. J., Ex. 2, at 2 (Condition 7) (“No changes shall be made in the design
or use of this project without the written approval of the District Coordinator
or Commission . . . .”). Therefore, little evidence supports the
need for finality in the permit process.
As a result, we find that the flexibility Appellee-Applicant seeks by
requesting consideration of its permit amendment application outweighs the
finality Appellants desire.
Accordingly,
based on the foregoing, it is hereby ORDERED and ADJUDGED that Appellants’
cross-motion for summary judgment is DENIED as to both issues presented, and
Appellee-Applicant’s cross-motion for summary judgment is GRANTED as to both issues
presented. A site visit and merits
hearing is scheduled for December 16, 2005, to resolve the remaining issue of
whether Appellee-Applicant’s proposed amendments will have an undue adverse
effect on the scenic or natural beauty of the area, or on aesthetic
considerations, warranting denial of the amendment under Criterion 8, as
directed by 10 V.S.A. § 6086(a)(8).
Done at
Thomas S. Durkin, Environmental Judge
[1] EBR 34(E)
states:
(E)
Stowe Club Highlands Analysis.
(1)
This rule governs applications to amend permit conditions which were included to
resolve issues critical to the district commission's or the board's issuance of
prior permit(s) pursuant to the criteria of 10 V.S.A. Section 6086(a).
Applications to amend other permit conditions are not subject to the
requirements of this section but must still satisfy the criteria of 10 V.S.A.
Section 6086(a) and other applicable provisions of these
rules.
(2)
In reviewing an application for amendment, the district commission or the board
should consider whether the permittee is merely seeking to relitigate the permit
condition or to undermine its purpose and intent. It must also determine whether
the need for flexibility arising from changes or policy considerations outweighs
the need for finality in the permitting process.
(3)
In balancing flexibility and finality, the district commission or the board
should consider the following, among other relevant
factors:
(a)
changes in facts, law or regulations beyond the permittee's
control;
(b)
changes in technology, construction, or operations which drive the need for the
amendment;
(c)
other factors including innovative or alternative design which provide for a
more efficient or effective means to mitigate the impact addressed by the permit
condition;
(d)
other important policy considerations, including the proposed amendment's
furtherance of the goals and objectives of duly adopted municipal
plans;
(e)
manifest error on the part of the district commission or the board in the
issuance of the permit condition;
(f)
the degree of reliance by the district commission, the board, or parties on
prior permit conditions or material representations of the applicant in prior
proceeding(s).
[2] Appellee-Applicant asserts that EBR
34(E) replaced the precedent of Stowe Club Highlands, 166 Vt. 33 (1996),
and for that reason, this Court need not conduct this second analysis. Since we have determined here that Rule
34(E) does not apply to these undisputed facts, we proceed to consider this
second analysis under Stowe Club Highlands and leave the question of
whether the Rule is a superseding one in all instances of permit amendment
review to another case. We note,
however, that EBR 34(E)(1) specifically provides that permit conditions that are
not deemed “critical . . . are not
subject to the requirements of this section,” thereby leaving some analysis to
be completed that is outside the purview of Rule 34(E).
[3]
Attach. to Appellee-Applicant’s Mot. for Summ. J., Ex. 2, at 3, Findings
of Fact, Conclusions of Law, and Order to Issue Permit #1R0468-15 states that a
buffer is required to protect a small stream passing to the east of the proposed
tennis courts.
[4]
We note that this representation was presented to the Court, not in the
form of the attorney’s written opinion of counsel, but in one Appellant’s
third-hand representation, contained in their Affidavit filed in support of
their Motion for Summary Judgment.
[5]
See Attach. to Appellants’ Mot. for Summ. J., Ex. R, which appears to be
Mountainside’s Warranty Deed to Appellants’ predecessor in title. This Deed is devoid of any specific
conveying language, covenant or restriction that could serve as evidence that
the developer represented that it intended to relinquish its right to further
develop the lands it retained in this
subdivision.